On this job we installed 1.3Km of underground conduit and cabling along the edge of a Dam Wall access road.

All cables & conduits were concrete encased the entire way before back filling could commence.

If your thinking Trenching or Conduit installation for your next project –

Think Country Tradies & Construction

Back filling and compacting at 200mm layers.

On this job we trenched and  installed all underground services:

  • Water Mains,
  • Sewer,
  • Telecom’s,
  • & Mains power

before back filling and reinstatement of the embankment.

Installation of conduits around the site.

Setting up conduits for bottom entry into the main switchboard. Lots of custom bends to enable a congested area under the switch board.

Access slab poured and cables pulled ready to install the main switch board. Now where’s that switch board gone 🙂